2008 Edition Summary of Changes
1. Small Boilers exemption now maximum 3 bar-litres v.1.5;
2. Check Insurance cover as it may impose additional limitationsno special requirements included within the Club’s insurance.
3. New Boilers to be inspected at least twice during construction commercial boilers built post 31 May 2002 must carry CE marking;
4. Steel boilers of 500 bar-litres and over to be dismounted and cladding removed at 7 years but Inspector has discretion to extend to 10 years (recording reasons), and to inspect without dismounting if all surfaces can be examined with cladding removed;
5. All boilers to carry a unique, indelible identification number which is visible when installed;
6. Boilers of 10 bar-litres or less need only have one water feed if two are impractical.
We have also identified a possible problem. For new boilers “water gauges must be fitted independently of other fittings including the manifold” in a number of model and prototype traction engine designs the top gauge is connected to the manifold. This requirement prevents adherence to prototype design.
M.J. February 2009